Developer profile, Hugh McNair, Savannah Ridge

SAVANNAH RIDGE CORPORATION

CONSTRUCTION CONSULTING / PROJECT MANAGEMENT

PRINCIPAL: Hugh S. McNair

PERSONAL DATA: Born February 3, 1940, in Augusta, Georgia. He is married to the former Cynthia Boliek and has two grown daughters. McNair, a learned pilot for over 30 years, experienced in many piston type aircraft and has achieved the level of Airline Transport Rating (ATP). He has logged more than 3000 hours flying time.

EDUCATION: Attended Savannah State Collage, Savannah, Georgia, and enhanced career knowledge through years of attendance of workshops and seminars. Military training includes air-traffic control training.

ORGANIZATIONS: United States Marine Corps Reserve 1961 through 1966, QBs’ Fliers’ Fraternity and various other local and civic organizations.

EXPERIENCE: McNair worked in the construction industry with several world-class firms. He served as the PROJECT MANAGER and or MANAGING DIRECTOR of many high profile construction, Design and Construction projects.

CONSTRUCTION EXPERIENCE: Most notable projects are:

  • During 16 years with Morrison Knudsen Company, McNair completed a new Community Hospital at Hilton Head Island, South Carolina and the following projects.
  • Norton Sound Regional Hospital at Nome, Alaska 1979. This challenging project in western Alaska consisted of a new addition and rehab of an existing facility. Despite the challenges of building in the romote regions of western arctic, the project was completed on time and within the planned budget.
  • St. Alphonsus Medical Center, Boise, Idaho new addition and renovations. Involvement in this project was interrupted by the most prestigious assignment to manage the construction of the new headquarters buildings for Morrison Knudsen Co., the employer.
  • The Morrison Knudsen Corporation headquarters included three new buildings of 500,000 square-feet and an 1100 space parking garage.
  • While with Henry C. Beck Co. at Dallas, Texas Southland Corporation’s "CITY PLACE CENTER", multi-use facility consisting of a 42 level high-rise tower and four 8 level mid-rise buildings totaling 2 million square feet of building above grade also, a 4000 space garage and basement levels (100’) below grade totaling 3 million square feet. The budget was $800 million in 1984. The project management group setup consisted of 3 teams of 40 people each provided staffing for specialty planning, scheduling and expediting. For example: design coordination, development and of the procurement plan and implementation, minority participation and safety programs, offshore stone facade & window wall system procurement, climbing-forms, hoisting, (10 cranes including 8 towers), 133 elevators, on site concrete plant etc.
  • After rejoining Morrison Knudsen Company assigned to direct the completion of a 750 unit military housing project for the Corps of Engineers at Fort Drum, New York. This assignment was followed by the projects below.
  • Boeing Aircraft Companies’ new Empennage Manufacturing Facility at Puyallup WA. This was a new facility where Morrison Knudsen Corporation’s MK Ferguson s Group provided Design and Build services for 500,000 square feet of manufacturing building, site-work and infrastructure along with helping with design and implementation of process equipment. Included with the building challenge were three 82,000 cubic feet autoclaves fabricated on site. These 600-ton vessels were moved into the building and installed on their foundations when the building was ready. This unusual plan shortened the schedule by six months. MK provided 283,966 engineering man-hours and performed $23 million worth of electrical work. This project was operational in 24 months.
  • Federal Reserve Bank’s new addition of a 12-story operations facility and remodel of an existing 15 level historic bank in downtown Cleveland Ohio. Left this project and Morrison Knudsen Corp. after completing a slurry-wall foundation with 5 levels of concrete construction below grade and achieving approval for a $110 million GMP.
  • Micron Technology Inc. of Boise, ID. This project was a grassroots semiconductor manufacturing facility at Lehi, UT. This project was shut down after spending $400 million enclosing 2.2 million square feet within 6 buildings, site work infrastructure and a 138 to 12.5 KV substation. The duration was only 8 months, which equates to about $2 million a day cash flow while supervising 90 + staff. There are many record-breaking accomplishments are summarized in a separate attachment.
  • Project Analysts is a firm that analyzes projects, helps a client’s staff organize and develop a plan resolving concerning issues and insuring control of the project. This service primarily helps avoid negative situations that causeing schedule and monetary surprise. This position continues on an as needed bases.

MICRON CONSTRUCTION Accomplishments

Ground roots, all new manufacturing plant at Lehi Utah June 25,1995 - February 1996

START UP: Work in the field started June 25, 1995 after only 3 months development of working drawings

SHUT DOWN: Work started slowing down during the December 1995 Holidays, Directions to stop work and demobilize came February 1996 after 8 months of intense design and construction work

ACCOMPLISHMENTS:

  • Moved 8.8 million cubic yards of earth (140,000 cy / day)
  • Placed 224,500 cubic yards of concrete (sometimes as much as 4,400 cubic Yards per day)
  • Erected 18,000 tons of structural steel, (around the clock)
  • Worked 3,062,072 craft labor hours with only 48 reportable accidents
  • Worked 336 shift/days (2/10 hour shifts)
  • 1800 drug-free craft workers during peek production periods
  • Installed a 180,000 S.F. administration complex including 400 computer work stations (Architect / Engineering, Contractors, Owner / User personnel
  • Enclosed and conditioned 2,373,000 square feet in six buildings
  • Used $480 million in 8 months (averaged $2 million a day)
  • Over thirty (30) miles of assorted piping
  • Design and Construction of an Electrical Substation (138 KV/12.5)
  • At the time, one of the most ambitious fast-track construction projects undertaken in the US. The project was featured in several articles in the ENR.

 

Home | About Us | History | Community OverviewAvailable Homesites | Links | Contact Us

Savannah Ridge Cabins
P.O. Box 4444, McCall, ID 83638
Phone: (208) 336-5560
Email: hugh@savannah-ridge.com

 Site maintained by Applied Marketing Group, Boise, Idaho
Copyright © 2002.  All Rights Reserved. Last Revised 01.19.04